CB Energy successfully completed the Western section of the 41 km Toowoomba Second range Crossing Project for NEXUS Delivery a Joint Venture of Acciona Infrastructure Australia and Ferrovial Agroman. The Western section stretches from Boundary Street at Cranley to the Gore Highway at Athol, a total of 21 km of roadway. The CB Energy team supplied and installed approximately 25 km of trenching with 48km of electrical and communications conduit. 504 electrical and communications pits, 253 footings for 12m Major Road streetlights and CCTV camera poles, 13 switchboard cabinets and 17.9 km of cable.

The CB Energy Toowoomba team completed the 22,565 man hours without an incident and ZERO Lost Time Injuries, a great achievement.

After CB Energy completed their own contract works and Nexus Delivery was in need of a competent contractor to complete the eastern section of the project, CB Energy took on the challenge and with a reduced time frame went above and beyond and delivered it in time.

Total installed on the project was approximately 58000m of electrical conduit, 750 Electrical Pits, over 300 Streetlights and foundations and 25000m of cable.

Total man hours 25711 still without a single incident or LTI.

To whom it may concern,
Nexus Delivery, a Joint Venture between Acciona Infrastructure Australia and Ferrovial Agroman, has worked with CB Energy, under my direct management, for the last 2.5 years constructing the Toowoomba Second Range Crossing. During that time CB Energy repeatedly proved to be a team player, always had the interests and goals of the project in mind and went above and beyond to achieve construction goals.
After CB Energy completed their own contract works and Nexus Delivery was in need of a competent contractor to complete additional scope of works under an important time pressure, due to the challenging relationship with other contractors providing a similar scope, and CB Energy took on the challenge and delivered such scope in a time manner, helping Nexus Delivery to achieve the partial opening milestone on time.

 

- Alberto Perez - ITS Manager